This newsletter is intended to provide updates on the new City of Oakdale Public Works facility. More information about the project can also be found on the New Public Works Facility webpage. 

Construction Progress

The Oakdale Public Works facility is nearing completion. The modified schedule now has an expected move in date of March 2026 with a tentative grand opening event slated for late spring. More information will be provided when details are finalized. 

The office area’s sheetrock has been installed and painting is underway. Locker room bathroom tile has been placed with installation of fixtures expected next month. The office areas will be the first section of the building fully completed.

The fleet storage area is nearing completion with lighting and heating systems now being installed. This is the largest space in the facility as it will safely store the Public Works vehicles.  

The mechanics and operational areas have all interior walls completed. Installation of critical items to maintain the fleet like vehicle lifts, cranes, and lube equipment are next for completion.

Site work progress includes completion of the salt storage shed, fuel island, perimeter fencing, and the first layer of pavement. Final site work, including landscaping will be done in the spring as soon as weather permits.

Gray and white building under construction in the winter with snow in parking area and several vehicles and white trucks in the lot

View of building exterior from 32nd Street N facing south shows progress on the office area.

interior of a building under construction with large concrete floor and exposed silver metal beams on ceiling with many brown boxes in large open space

Heating and lighting systems are being installed in the fleet storage area.

Construction area of a new building with small openings shows blue walls and open windows with blue paint and a yellow painting dolly in the middle on new concrete floors that are dusty

Painting of the staff office area is underway.

white fuel tank covered by a structure that has a blue flat roof with white on the interior with copper/brown beans supporting with snow on the ground

The fuel island is now complete. 

white arched struture with beams inside shows storage area with concrete walls and base in a concrete area outdoors

The salt storage shed is now complete.

PROJECT CONTACT
Please direct questions to: 
Don Theisen
Project Owner's Representative - City of Oakdale
Email Don Theisen
Phone: 
651-315-4860

IMPORTANT LINKS
New Public Works Facility Webpage
Subscribe to Project Updates
City of Oakdale Website

Share on Facebook
Share on Twitter
Share via Email

Copyright 2025. City of Oakdale. All Rights Reserved.
1584 Hadley Avenue N, Oakdale, MN 55128

Powered by
CivicSend - A product of CivicPlus