Construction has begun on this year’s Street Improvement Project. The contractor has split the project into four areas for coordination and scheduling. Project Map
- Area 1: Upper 5th Street N (Greenway Avenue N to Grovner Avenue N), 5th Street N, and 5th Street Court N
- Area 2: 6th Street N, 4th Street N, 3rd Street N, Grenadier Avenue N, and Gresham Avenue N
- Area 3: 1st Street North and Greystone Avenue N
- Area 4: Grovner Avenue N and Upper 5th Street N (Grovner Avenue N to Hadley Avenue N)
Improvements on Phase 1 and Phase 3 include the removal and replacement of water main and services, miscellaneous storm sewer repairs, curb and gutter replacement, driveway apron replacement, new gravel and sand section, full asphalt replacement, and street light replacement.
The improvements in Phase 2 include all the following except 4th Street N: miscellaneous storm and sanitary and water main repairs, full curb and gutter replacement with new driveway aprons, new gravel and sand section, full asphalt replacement, and street light replacement. Work on 4th Street N will have spot curb replacement, and miscellaneous storm and water main repairs, full asphalt replacement, and lighting replacement.
The improvements in Phase 4 include spot curb replacement, miscellaneous storm and water main repairs, full asphalt replacement, and lighting replacement.
McNamara Contracting is the contractor for this project. They have successfully completed many similar local projects. All project work is scheduled to be completed by the end of September.
Current and Planned Work
Area 1: Upper 5th Street N (Greenway Avenue N to Grovner Avenue N), 5th Street N, and 5th Street Court N)
- All disturbed areas are currently being sodded. Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
- The final layer of asphalt is tentatively planned for Friday, September 26. Residents will be notified in advance of this work.
Area 2: 6th Street N, 4th Street N, 3rd Street N, Grenadier Avenue N, and Gresham Avenue N
- All disturbed areas are currently being sodded. Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
- The final layer of asphalt is tentatively planned for Friday, September 26. Residents will be notified in advance of this work.
Area 3: 1st Street N and Greystone Avenue N
- All disturbed areas are currently being sodded. Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
- A sand filtration bench is being installed in the pond on the southeast corner of Greystone Avenue N and Hudson Boulevard. This work is expected to be completed early next week.
- The final layer of asphalt is tentatively planned for Friday, September 26. Residents will be notified in advance of this work.
Area 4: Grovner Avenue N and Upper 5th Street N (Grovner Avenue N to Hadley Avenue N)
- All disturbed areas are currently being sodded. Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
- The final layer of asphalt is tentatively planned for Friday, September 26. Residents will be notified in advance of this work.
Reminders
As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7 AM to 7 PM within the project area unless instructed to by the contractor to accommodate driveway work. This will help the contractor to work more efficiently and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.
If you have any questions regarding this project, please feel free to call:
- Mike LaDoux, E.I.T, Project Representative with SEH 651-256-0438
- Brian Bachmeier, P.E., Consulting City Engineer 651-730-2730