Construction has begun on this year’s Mill and Overlay Project. The project area is Hadley Avenue N from 10th Street N to Hallmark Avenue N.
General Work Schedule
During the first two to four weeks, the contractor plans the following work:
- Install temporary construction signing and erosion control devices.
- Remove and replace the existing bike trail pavement.
- Remove and replace isolated sections of damaged concrete curb and gutter.
- Repair some storm sewer catch basins and water valve boxes.
- Restore disturbed boulevard areas.
- Replace street lights with decorative aluminum poles and LED fixtures.
During the last one to two weeks, the contractor plans the following work:
- Mill off the top layer of asphalt pavement.
- Repave the top layer of asphalt pavement.
- Restripe the roadway about three days after paving.
Current and Planned Work
- There will be crews sawcutting curb and prepping for removal on Thursday, September 11 and Friday, September 12.
- Removals of any damaged curb and concrete will take place on Monday, September 15 and Tuesday, September 16.
- New concrete curb and gutter will be poured in the removed areas starting on Wednesday, September 17 and continue to the end of the week.
- Topsoil and restoration will occur the week after areas are disturbed.
As construction progresses, please remember to drive carefully and use caution when driving through the work area. Keep children a safe distance from the equipment and construction activity. We appreciate your cooperation and patience during this work.
If you have any questions regarding this project, please feel free to call:
- Jeff Thene, Project Representative with SEH 651-755-4437
- Brian Bachmeier, P.E., Consulting City Engineer 651-730-2730