Construction has begun on this year’s Mill and Overlay Project. The project area is Hadley Avenue N from 10th Street N to Hallmark Avenue N.
General Work Schedule
During the first two to four weeks, the contractor plans the following work:
- Install temporary construction signing and erosion control devices.
- Remove and replace the existing bike trail pavement.
- Remove and replace isolated sections of damaged concrete curb and gutter.
- Repair some storm sewer catch basins and water valve boxes.
- Restore disturbed boulevard areas.
- Replace street lights with decorative aluminum poles and LED fixtures.
During the last one to two weeks, the contractor plans the following work:
- Mill off the top layer of asphalt pavement.
- Repave the top layer of asphalt pavement.
- Restripe the roadway about three days after paving.
Current and Planned Work
- The bike and pedestrian trail along Hadley Avenue N is currently closed.
- Grading of the bike and pedestrian trail will start on Thursday, August 21. This is planned to be completed on Tuesday, August 26.
- The bike and pedestrian trail will be paved on Wednesday, August 27 and be completed Thursday, August 28.
- New concrete curb and gutter along Hadley Avenue N is tentatively scheduled to start Friday, August 29. This will take five days to complete. Only damaged or non-functional curb will be removed and replaced.
As construction progresses, please remember to drive carefully and use caution when driving through the work area. Keep children a safe distance from the equipment and construction activity. We appreciate your cooperation and patience during this work.
If you have any questions regarding this project, please feel free to call:
- Jeff Thene, Project Representative with SEH 651-755-4437
- Brian Bachmeier, P.E., Consulting City Engineer 651-730-2730