Construction has begun on this year’s Mill and Overlay Project. The project area is Hadley Avenue N from 10th Street N to Hallmark Avenue N.
General Work Schedule
During the first two to four weeks, the contractor plans the following work:
- Install temporary construction signing and erosion control devices.
- Remove and replace the existing bike trail pavement.
- Remove and replace isolated sections of damaged concrete curb and gutter.
- Repair some storm sewer catch basins and water valve boxes.
- Restore disturbed boulevard areas.
- Replace street lights with decorative aluminum poles and LED fixtures.
During the last one to two weeks, the contractor plans the following work:
- Mill off the top layer of asphalt pavement.
- Repave the top layer of asphalt pavement.
- Restripe the roadway about three days after paving.
Current and Planned Work
The bike and pedestrian trails along Hadley Avenue N will be closed starting the week of Monday, August 18. Trail work is anticipated to last two weeks
As construction progresses, please remember to drive carefully and use caution when driving through the work area. Keep children a safe distance from the equipment and construction activity. We appreciate your cooperation and patience during this work.
If you have any questions regarding this project, please feel free to call:
- Jeff Thene, Project Representative with SEH 651-755-4437
- Brian Bachmeier, P.E., Consulting City Engineer 651-730-2730