Construction vehicle on road torn up in residential neighborhood

2025 OAKDALE

Street Improvement Project Update

July 3, 2025

Each summer, the City of Oakdale provides weekly construction updates on the annual Street Improvement Program projects. For more information on this year's projects, visit the City of Oakdale Engineering Projects webpage.

Construction has begun on this year’s Street Improvement Project. The contractor has split the project into four areas for coordination and scheduling. Project Map

- Area 1: Upper 5th Street N (Greenway Avenue N to Grovner Avenue N), 5th Street N, and 5th Street Court N 
- Area 2:  6th Street N, 4th Street N, 3rd Street N, Grenadier Avenue N, and Gresham Avenue N 
- Area 3:  1st Street North and Greystone Avenue N 
- Area 4:  Grovner Avenue N and Upper 5th Street N (Grovner Avenue N to Hadley Avenue N) 

Improvements on Phase 1 and Phase 3 include the removal and replacement of water main and services, miscellaneous storm sewer repairs, curb and gutter replacement, driveway apron replacement, new gravel and sand section, full asphalt replacement, and street light replacement.

The improvements in Phase 2 include all the following except 4th Street N: miscellaneous storm and sanitary and water main repairs, full curb and gutter replacement with new driveway aprons, new gravel and sand section, full asphalt replacement, and street light replacement. Work on 4th Street N will have spot curb replacement, and miscellaneous storm and water main repairs, full asphalt replacement, and lighting replacement.

The improvements in Phase 4 include spot curb replacement, miscellaneous storm and water main repairs, full asphalt replacement, and lighting replacement. 

McNamara Contracting is the contractor for this project. They have successfully completed many similar local projects. All project work is scheduled to be completed by the end of September.

Current and Planned Work

Area 1: Upper 5th Street N (Greenway Avenue N to Grovner Avenue N), 5th Street N, and 5th Street Court N)
- All water main work is complete. Residents should be back on City water.
- The contractor has begun excavating the entire street to install a new City standard gravel and sand section in the roadway. Upper 5th Street N was completed on Wednesday, July 2. 5th Street N and 5th Street Court N will begin Thursday, July 3 and continue until mid-next week. The contractor is responsible for keeping access to driveways. However, there will be brief periods when equipment or digging is happening directly in front of driveways. Please be patient as this work takes place.
- There are now concrete curb stakes installed. Please do not disturb these stakes, as they are essential for curb location and elevation.
- Installation of concrete curb and driveway aprons is planned for July 16. Residents will receive more information regarding access and parking before that time. 
- The first layer of asphalt is planned for the third week in July.

Area 2: 6th Street N, 4th Street N, 3rd Street N, Grenadier Avenue N, and Gresham Avenue N
- Installation of new concrete curb and driveway aprons is complete.
- Topsoil and restoration work has begun.
- Those that have asphalt driveways will have the gaps between driveway and apron patched next week.  

Area 3: 1st Street North and Greystone Avenue N
- Work is now tentatively planned to begin the third week in July.

Area 4: Grovner Avenue N and Upper 5th Street N (Grovner Avenue N to Hadley Avenue N) 
- Work is now tentatively planned to begin the third week in July.

Reminders

As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7 AM to 7 PM within the project area unless instructed to by the contractor to accommodate driveway work. This will help the contractor to work more efficiently and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.

If you have any questions regarding this project, please feel free to call:
- Mike LaDoux, E.I.T, Project Representative with SEH 651-256-0438
- Brian Bachmeier, P.E., Consulting City Engineer 651-730-2730

Share on Facebook
Share on Twitter
Share via Email

Copyright 2025. City of Oakdale. All Rights Reserved.
1584 Hadley Avenue N, Oakdale, MN 55128

Powered by
CivicSend - A product of CivicPlus