Construction has begun on this year’s Street Improvement Project. The contractor has split the project into four areas for coordination and scheduling.
- Area 1: 46th Street N, 47th Street N, 48th Street N and 49th Street N (From Hadley Avenue N to the East) Area 1 Map
- Area 2: Hadley Avenue N from 40th Street N to 50th Street N Area 2 Map
- Area 3: Oakdale Nature Preserve Trail Reconstruction Area 3 Map
- Area 4: North Fire Station Parking Lot Reconstruction Area 4 Map
Improvements on Hadley Avenue N include miscellaneous storm sewer repairs, spot curb and gutter replacement, full asphalt replacement, street light replacement and bike trail reconstruction on the west side of Hadley Avenue N.
The improvements in the residential areas east of Hadley Avenue N include miscellaneous storm, sanitary and water main repairs, spot curb and gutter replacement, street light replacement and full asphalt pavement replacement.
Dresel Contracting is the contractor for this project. They have successfully completed many similar local projects. All project work is scheduled to be completed by the end of September.
Current and Planned Work
Area 1: 46th Street N, 47th Street N, 48th Street N and 49th Street N (From Hadley Avenue N to the East)
- Old light poles and concrete bases are being removed and replaced. This work will be complete today, Friday, September 13.
- Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
Area 2: Hadley Avenue N (40th Street N to 50th Street N)
- New light pole installation on Hadley Avenue N is now tentatively planned for late-September as the City is waiting for light components to ship. Paving will commence after light poles are installed.
- The contractor will be installing a new concrete base at Hadley Avenue N and 43rd Street N early next week.
- Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.
Area 3: Oakdale Nature Preserve Trail Reconstruction
- All work is complete. The contractor will keep an eye on the restoration throughout the trail and will address any areas of concern as necessary.
Area 4: North Fire Station Parking Lot Reconstruction
- The parking lot will be striped at the same time as Hadley Avenue N. The schedule is pending on the Hadley Avenue N paving.
Reminders
As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7 AM to 7 PM within the project area unless instructed to by the contractor to accommodate driveway work. This will help the contractor to work more efficiently and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.
If you have any questions regarding this project, please feel free to call:
- Mike LaDoux, E.I.T, Project Representative with SEH 651-256-0438
- Brian Bachmeier, P.E., Consulting City Engineer 651-730-2730