Construction vehicle on road torn up in residential neighborhood

2024 OAKDALE

Street Improvement Project Update

SEPTEMBER 5, 2024

Each summer, the City of Oakdale provides weekly construction updates on the annual Street Improvement Program projects. For more information on this year's projects, visit the City of Oakdale Engineering Projects webpage.

Construction has begun on this year’s Street Improvement Project. The contractor has split the project into four areas for coordination and scheduling.

- Area 1:  46th Street N, 47th Street N, 48th Street N and 49th Street N (From Hadley Avenue N to the East) Area 1 Map
- Area 2:  Hadley Avenue N from 40th Street N to 50th Street N Area 2 Map
- Area 3:  Oakdale Nature Preserve Trail Reconstruction Area 3 Map
- Area 4:  North Fire Station Parking Lot Reconstruction Area 4 Map

Improvements on Hadley Avenue N include miscellaneous storm sewer repairs, spot curb and gutter replacement, full asphalt replacement, street light replacement and bike trail reconstruction on the west side of Hadley Avenue N. 

The improvements in the residential areas east of Hadley Avenue N include miscellaneous storm, sanitary and water main repairs, spot curb and gutter replacement, street light replacement and full asphalt pavement replacement. 

Dresel Contracting is the contractor for this project. They have successfully completed many similar local projects. All project work is scheduled to be completed by the end of September.

Current and Planned Work

Area 1: 46th Street N, 47th Street N, 48th Street N and 49th Street N (From Hadley Avenue N to the East)
- Old light poles and concrete bases will be removed and replaced with new concrete light poles starting Friday, September 6. This work will continue into the following week.
- Please help water your sod so it grows!  The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.

Area 2: Hadley Avenue N (40th Street N to 50th Street N)
- New light pole installation on Hadley Avenue N is tentatively planned for mid-September as the City is waiting for light components to ship.
- Please help water your sod so it grows! The contractor will also water for the first 30 days only. Any sod that is acceptable after 30 days will not be replaced. See the sod care sheet for more information.

Area 3: Oakdale Nature Preserve Trail Reconstruction
- All work is complete. The contractor will keep an eye on the restoration throughout the trail and will address any areas of concern as necessary.

Area 4: North Fire Station Parking Lot Reconstruction
- The final layer of asphalt is tentatively scheduled for Monday, September 9.

Reminders

As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7 AM to 7 PM within the project area unless instructed to by the contractor to accommodate driveway work. This will help the contractor to work more efficiently and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.

If you have any questions regarding this project, please feel free to call:
- Mike LaDoux, E.I.T, Project Representative with SEH 651-256-0438
- Brian Bachmeier, P.E., Consulting City Engineer 651-730-2730

Share on Facebook
Share on Twitter
Share via Email

Copyright 2024. City of Oakdale. All Rights Reserved.
1584 Hadley Avenue N, Oakdale, MN 55128

Powered by
CivicSend - A product of CivicPlus