Construction is now complete on this year’s street improvement project. The contractor (Miller Excavating) split the project into smaller areas for coordination and scheduling (see
project area map on the City of Oakdale website, www.ci.oakdale.mn.us):
- 31st Avenue neighborhood west of Ideal Avenue and north of Stillwater Boulevard (Anna's Grove).
- 4th Street between Helmo Avenue and Inwood Avenue.
- Imperial Avenue/Oak Marsh Drive/3rd Street from 4th Street to Inwood Avenue.
The improvements included miscellaneous storm sewer/sanitary sewer/watermain repairs and replacement, replacement of isolated sections of structurally damaged curb and gutter, repaving of the asphalt pavement section, installation of new street lighting, and some trail and walk improvements. On 4th Street, the rural roadway with ditches was replaced with an urban roadway with curb and storm sewer and the trail was reconstructed.
This is the final update for 2022 as construction is now complete.Area 1: 31st Avenue Neighborhood west of Ideal Avenue and north of Stillwater Boulevard (Anna's Grove)Area 2: 4th Street between Helmo Avenue and Inwood AvenueArea 3: Imperial Avenue/Oak Marsh Drive/3rd Street from 4th Street to Inwood Avenue- Work in area 3 is complete. The contractor has just a small amount of pavement striping left to finish on 4th Street as the snow delayed that Friday, but it should be completed Saturday.
If you notice some project clean up items remaining, please contact a representative below to review.
Thank you for your cooperation during this project!
Mike LaDoux, 651.256.0438, On Site Project Representative, SEH
Brian Bachmeier, 651.704.9970, Oakdale Consulting City Engineer
Todd Blank, 651.490.2017, Project Manager, SEH