Construction continues on this year’s street improvement project. The contractor has split the project into smaller areas for coordination and scheduling: - Area 1: The Shenandoah neighborhood located east of I-694 and north of 50th Street. View area 1 map.
- Area 2: The commercial industrial areas east and west of I-694, north of 4th Street and south of 10th Street. View area 2 map.
- Area 3: The Oakdale Park trail from Hadley Avenue to the Discovery Center and west to Granada Avenue. View area 3 map.
The improvements include miscellaneous storm sewer/sanitary sewer/water main repairs and replacement, replacement of isolated sections of structurally damaged curb and gutter, repaving of the asphalt pavement section, installation of new street lighting, and some trail and walk improvements.
MN Paving is the contractor for this project. They have successfully completed many similar projects for the City. All project work is scheduled to be complete by early September.
|
|
|
|
Current and Planned Work Area 1
Shenandoah Valley neighborhood located east of I-694 and north of 50th Street- Isolated areas of damaged concrete curb and gutter have been removed and replaced, and driveways are now being patched.
- Reclaiming the existing asphalt road surface and aggregate base is planned to begin on Tuesday, June 8, and will take about 3 days to complete. The roadway gravel will then be graded for new pavement. Access will be provided during this, but please use caution around the work equipment and crews.
- The Gateway Trail connection pavement will be removed early next week and the trail will then be reconstructed with excess gravel from the street area.
- The lighting contractor is continuing installation of the new underground wiring system and then will install new poles. Between the other work happening, this will take about three weeks to complete.
Area 2 Commercial-industrial area east of I-694, north of 4th Street and south of 10th StreetEast of I-694- The pipe contractor is finished with storm sewer and watermain repairs.
- Isolated areas of damaged curb and gutter replacement have been removed and new curb will be installed in these areas over the next week or so.
West of I-694- The pipe contractor is beginning storm sewer and watermain repairs. This work will take about 2 weeks to complete.
Area 3Oakdale Park trail from Hadley Avenue to the Discovery Center and west to Granada Avenue- Work is planned to start here in early August.
As construction progresses, please use caution traveling within the project area. Also, please do not park vehicles on the street from 7 am to 7 pm within the project area unless instructed to by the contractor to accommodate driveway work. This will help the contractor to work more efficiently, and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation. If there are any questions or comments regarding the project, please contact one of the following people: - Joe Meemken, 651-724-5588, On Site Project Representative, SEH
- Brian Bachmeier, 651-730-2730, Oakdale Public Works Director/City Engineer
- Todd Blank, 651-490-2017, Project Manager, SEH
|
|
|
|