Posted on: January 13, 2023

City and Other Agency Construction Projects Update

Construction

City of Oakdale Construction Projects:

  • 40th Street East of Interstate 694 The private utilities are working through the winter relocating their facilities. The City’s contractor will be remobilizing on site after spring load limits are lifted (usually mid- to late-April). It is anticipated the road will remain closed until the improvements are completed in June with the roadway reopening prior to July 4.
  • Water Tower 2 Repainting (located on the south end of Eberle Park) – Construction activity will start in mid-March with T-Mobile removing their cellular equipment from the water tower. They will be placing a temporary cellular tower northwest of the water tower. The painting contractor is expected to start in mid-April with completion in mid-June.
  • Lift Station 6 Replacement/Relocation (located at the intersection of Stillwater Boulevard & Ideal Avenue) – The contractor will be remobilizing on the site this spring and completing the project by July.

Other Agency Projects:

  • METRO Gold Line BRT Project from TH 120 to Helmo Avenue along Hudson Blvd, 4th Street, and Helmo Avenue – The Metropolitan Council is building a Bus Rapid Transit way. The contractor for the project is Ames Construction. The roadwork in Oakdale will progress from east to west with the Helmo-4th  Street improvements from the new bridge to Hadley Avenue being completed in 2023. It is anticipated that 4th Street between Helmo Avenue and Hadley Avenue will be closed from mid-April to mid-September for construction of the bridge over Interstate 694. Hadley south of 4th Street and Hudson Boulevard from Hadley to TH 120 will be completed in 2024. See METRO Gold Line BRT project