The neighborhoods in the 2021 project area have streets that are at the end of their service life. The pavement in these areas is severely cracked, and pavement has had to be patched by hand year after year. Some project areas contain additional problems such as drainage issues.
Proposed improvements for the 2021 street improvement project include:
The total estimated cost for the project is $3,670,000. The City will finance 60% of the total project, and the balance will be paid by special assessments.
November 4, 2020 | Neighborhood meeting |
December 8, 2020 | Feasibility report to City Council |
January 26, 2021 | Public hearings |
March 23, 2021 | Plan approval |
April 27, 2021 | Award contract |
May 2021 | Start construction |
August 2021 | Substantial completion |