2019 Street Improvement Updates

July 19, 2019

Construction has begun on this year’s street improvement project which covers the Partridge Estates and Heather Ridge neighborhoods. The improvements include miscellaneous storm sewer/sanitary sewer/water main repairs and replacement, replacement of isolated sections of structurally damaged curb and gutter, repaving of the asphalt pavement section, and installation of uniform street lighting. It also includes replacing the top surface of pavement on Helmo Avenue from 15th Street to Upper 23rd Street.
 
T.A. Schifsky & Sons, Inc. is the Contractor for this project. They have successfully completed many similar projects for the City.  This work will be done in phases by area to help minimize disruption. All project work is scheduled to be complete by early September.

Project Areas:

Current and Planned Work


Partridge Estates Area

  • Lighting work in this area has begun with the installation of the new wiring system.  Street light installation will follow.
  • Boulevard sodding will be done after the lighting work is complete.

Heather Ridge Area

  • Underground pipe work is complete in this area.
  • Hayward Road, Heather Ridge Road from Hayward to 46th Street, Heather Way, 46th Street and 46th Street Court: Spot curb replacement and concrete driveway patching is now complete. Gravel is being shaped in preparation for paving. The first layer of asphalt paving is planned for July 24 depending upon weather.
  • The remaining streets on the south end are planned to be reclaimed into gravel about mid-August.
  • The Dog Park on Helena Road is closed now for improvements. This includes installation of a drinking fountain, installation of parking lot curb and pavement, and installation of a storm water treatment raingarden. We apologize for the inconvenience, but it is for the safety of people and their pets while this work is done. 
  • City crews plan are finishing the replacement of the play equipment at Oakfield Park. 
  • Excel Gas crews have finished the gas main and service replacement work. This work is separate from the City project work. They have begun their own grass restoration with seeding in areas that have been paved. 

Helmo Avenue mill & overlay

  • Storm sewer repairs, Manhole casting repairs and street lighting replacement are being done now. Next week spot curb and gutter repairs and pedestrian ramp work is scheduled. The top layer of asphalt pavement is planned to be milled and repaved in early August.
As construction progresses, please use caution traveling within the project area.  Also, please do not park vehicles on the street from 7AM to 7PM within the project area unless instructed to by the Contractor to accommodate driveway work. This will help the Contractor to work more efficiently, and will create a safer work zone. Thank you, as always, for your ongoing patience and cooperation.
 
If there are any questions or comments regarding the project, please contact one of the following people:
  • Joe Meemken, 651-724-5588, On Site Project Representative, SEH
  • Jeff Thene, 651-490-2049, Sr. On Site Project Representative, SEH
  • Brian Bachmeier, 651-730-2730, Oakdale Public Works Director/City Engineer
  • Todd Blank, 651-490-2017, Project Manager, SEH